HSE DEPARTMENT
CONTROLLED DOCUMENT
QSHE Management System Manual
Job Safety Analysis and Project Planning Document
Document Number: QHSE-TSI-CF-8.0
Revision Number:7
Date: 6/15/2025
Approver: Jeremy Melder

HAZARD ANALYSIS

STEP SEQUENCE OF JOB PROCEDURESPOTENTIAL HAZARDS (SPECIFIC)ACTIONS TO REDUCE/ELIMINATE HAZARDS
● HANDLNG PLUG, TOOL GUIDE, AND LIFT PLUG INSTALLATION● IMPROPER INSTALLATION OF THE TOOL GUIDE OR LIFT PLUG COULD RESULT IN THE DROPPING OF A JOINT CAUSING DAMAGES TO EQUIPMENT, INJURIES, OR EVEN DEATH● READ ALL THE PROCEDURES OF THE REQUIREMENTS OF HTE INSTALLATION OF HANDLING DEVICE

● GET PROPER INSTRUCTIONS AND TRAINING BEFORE PERFORMING TASK ON YOUR OWN

● IT IS IMPERATIVE THAT OEM/API PROCEDURES FOR INSTALLATION OF HANDKLING DEVICE IS FOLLOWED TO THE LETTER. FAILURE TO ADHERE DAN RESULT IN POTENTIAL PERSONNEL INJURY, DEATH AND/OR DAMAGES TO JOINTS/EQUIPMENT
● REMOVAL OF PIN PROTECTORS AND CLEANING OF PIN THREADS● USING A HAMMER TO REMOVE STUCK PROTECTORS COULD RESULT IN INJURIES

● THE DEGREASER TO CLEAN THE THREADS CAN GET INTO YOUR ETES IF NOT WEARING PROPER PROTECTION
● GIVE PROPER INSTRUCTIONS OF THE INSTALLATION OF PROTECTORS TO PREVENT THEM FROM GETTING STUCK

● IF STUCK ON CASING, USE CHAIN TONGS TO REMOVE PROTECTORS

● WHEN USING CHEMICALS TO CLEAN THEADS WEAR GLOVES AND SAFETY GLASSES TO PROTECT YOU
● PERFORM THREE DUMP TESTS/DEAD STICKS● DURING THE DUMP TEST A JOINT COULD BE KICKED OVER INTO THE BOARD

● IF THE TONGS ARE NOT LEVEL OR THE SNUB LINE NOT AT 90° THEN IMPROPER TORQUE READINGS ARE POSSIBLE
● WHILE DUMP TESTS ARE BEING PERFORMED WATCH THE EQUIPMENT AND JOINT TO MAKE SURE DAMAGES ARE NOT INCURRED

● CONFIRM TONGS ARE LEVEL AND SNUB LINE IS AT THE REQUIRED ANGLE TO GET ACCURATE TORQUE READINGS
● RUN 15-20 JOINTS AND EVALUATE● PAUSE TO REVIEW THE RUNNING OF THE CONNECTION AND MAKE ADJUSTMENTS THAT NEED TO BE DONE TO THE EQUIPMENT OR PROCEDURES TO ENSURE A SAFE SMOOTH JOB
● MAKE UP CONNECTIONS TO PROPER TORQUE● MAKING UP CONNECTIONS WITHOUT VERIFICATION OF THE CASING STENCILS COMPARED TO CONNECTION DATASHEETSJ WILL RESULT IN RUNNING IMPROPERLY AND COULD RESULT IN A CASING FAILURE● ALWAYS VERIFY THE PIPE STENCILS AND COMPARE TO YOUR CONNECTION DATASHEETS TO MAKE UP CONNECTION TO THE CORRECT TORQUE

● REVIEW THE RUNNING PROCEDURES TO ENSURE PROPER HANDLING AND CARE IS TAKEN

● VISUALLY VERIFY PROPER MAKEUP WHEN CASING HAS INDICATION MARKING LIKE A TRIANGLE STAMP
● TORQUE TURN EQUIPMENT CABLES● UNSECURE CABLES COULD BE A DISTRACTION IF HANGING IN THE WAY OF THE TONG OPERATORS OR BECOME A TRIP HAZARD● MAKE SURE TO SECURE ALL CABLES THAT ARE ON THE TONGS AND ALSO GOING TO THE TORQUE MONITORING COMPUTER

● PERIODICALLY CHECK THE EQUIPMENT IS SECURE AND MAKE ADJUSTMENTS IF NECESSARY

● KEEP AREA CLEAN AND CABLES WRAPPED SO YOU ARE NOT CREATING TRIP HAZARDS
● CHANGING OUT EQUIPMENT● NOT VERIFIYING OR MONITORING EQUIPMENT THAT IS CHANGED OUT COULD RESULT IN IMPROPER EQUIPMENT USED CAUSING DAMAGES OR INJURIES● WHILE EQUIPMENT IS BEING CHANGEDJ OUT, MONITOR THE WORKING CREW TO ENSURE PROPER EQUIPMENT IS GOING TO BE UTILIZED.

● IF UNABLE TO MONITOR THE WORKING CREW, THEN BEFORE OPERATIONS ARE TO BEGIN AGAIN VERIFY NEW EQUIPMENT IS ACCEPTABLE TO USE AND IN GOOD WORKING CONDITION● IT IS ALWAYS GOOD PRACTICE TO HOLD A JSA TO G OVER THE DETAILS OF EQUIPMENT THAT IS RIGGED DOWN, WHERE IT SHOULD GO, AND THE EXACT EQUIPMENT THAT WILL BE RIGGED UP FOR USE
● COMMUNICATE THE RUNNING OF ACCESSORIES AND THE MARKING OF CENTRALIZERS● NOT COMMUNICATING WITH ALL PERSONNEL DURING THE CASING RUN OR BEFORE ACCESSORIES ARE TO BE MADE UP COULD LEAD TO THEIR MISPLACEMENT IN THE STRING● IN THE PREJOB MEETING COVER THE PLACEMENT OF ALL ACCESSORIES GOING INTO THE STRING

● COMMUNICATE 10 JOINTS BEFORE RUNNING AN ACCESSORY OR SPECIAL ITEM SO EVERYONE IS AWARE AND CAN PREPARE FOR THE UPCOMING TASK

Safety First - Safety Always
Plan and Execute for Success
Page: 3 of 8