![]() | HSE DEPARTMENT CONTROLLED DOCUMENT QSHE Management System Manual Job Safety Analysis and Project Planning Document | Document Number: QHSE-TSI-CF-8.0 Revision Number:7 Date: 6/15/2025 Approver: Jeremy Melder |
| STEP SEQUENCE OF JOB PROCEDURES | POTENTIAL HAZARDS (SPECIFIC) | ACTIONS TO REDUCE/ELIMINATE HAZARDS |
| ● TRANSPORT CASING RUNNING TOOLS AND TORQUE MONITORING EQUIPMENT TO RIG FLOOR | ● EQUIPMENT/TOOLS COULD BE DROPPED DOWN THE RIG STAIRS WHILE CARRYING BYHAND TO THE RIG FLOOR ● EQUIPMENT COULD FALL DOWN THE V-DOOR FROM STRAPS NOT PROPERLY RATED FOR WEIGHT, WORN OUT, OR NOT PROPERLY SECURED WHILE HOISTED TO THE RIG FLOOR | ● LOAD EQUIPMENT OR TOOLS INTO A BACKPACK TO TRANPSORT BY HAND UP THE RIG STAIRS ● ALWAYS MAINTAIN 3 POINTS OF CONTACT WHILE GOING UP AND DOWN RIG STAIRS ● DOUBLE CHECK THE CONDITION OF HOIST STRAPS, THEIR RATING, AND THAT THEY ARE SECURED TO EQUIPMENT BEFORE LIFTING TO RIG FLOOR. >● NEVER STAND UNDER OR IN THE LINE OF FIRE OF SUSPENDED LOADS GOING UP OR DOWN THE V-DOOR |
| ● CONDUCT A PREJOB SAFETY MEETING TO DISCUSS EQUIPMENT RIG UP, TALLY DETAILS, AND HANDLING/PROCEDURES OF CASING RUN | ● REVIEW JSA WITH ALL PERSONNEL AND COMPANY REP THEN SIGN OFF ON SAFETY MEETING SHEET ● GIVE ALL PERSONNEL A CHANCE TO ADD COMMENTS, CONCERNS, OR GUIDELINES TO ALL SAFETY REQUIREMENTS AND PROCEDURES ● MAKE ADJUSTMENTS OR ADDITIONS TO JSA AT THE END OF THE TSI JSA DOCUMENT &$9679; CONDUCT A JSA WHEN NEW RIG CREW BEGINS WORK | |
| ● RIG UP CASING CREW AND TORQUE MONITORING EQUIPMENT | ● EQUIPMENT TAILED IN COULD SWING INTO OTHER EQUIPMENT OR PERSONNEL | ● NEVER TURN YOUR BACK TO LOADS BEING TAILED IN AND STAND CLEAR UNTIL THE LOAD IS POSITIONED |
| ● STRING ACCESSORIES BROUGHT UP TO RIG FLOOR | ● HANDS AND FEET COULD BE INJURED WHILE RIGGING UP EQUIPMENT ● TRIPS AND FALLS FROM POTENTIAL HAZARDS AS EQUIPMENT GETS ORGANIZED AND INTO CORRECT POSITION | ● KEEP CABLES FROM EQUIPMENT ORGANIZED AND OUT OF THE WAY TO PREVENT DAMAGES OR TRIP HAZARDS ● ALWAYS WEAR GLOVES AND BE MINDFUL OF YOUR HAND AND FEET PLACEMENT WHILE WORKING ● KEEP AREA AS CLEAR AS POSSIBLE FROM TRIP HAZARDS IN THE EVENT YOU NEED TO EVACUATE THE RIG FLOOR IMMEDIATELY |
| ● WELL CONTROL ON THE RIG FLOOR | ● NOT HAVING WELL CONTROL ON THE RIG FLOOR COULD BE THE DIFFERENCE IN CONTROLLING THE WELL OR NOT | ● BEFORE THE CASING RUN BEGINS, HAVE ALL WELL CONTROL EQUIPMENT ON THE RIG FLOOR, READY TO BE INSTALLED ● IN THE PREJOB MEETING, GO OVER THE ACTIONS AND WELL CONTROL EQUIPMENT IN THE EVENT SECURING THE WELL IS NEEDED |
| ● RUNNIG CASING/TUBING | ● CONTROL OF THE INCOMING JOINT COULD BE LOST WHICH COULD SWING IN, STRIKING PERSONNEL ● YOU COULD BE CAUGHT BETWEEN EQUIPMENT OR PIPE AND THE DERRICK LEG OR OTHER EQUIPMENT IF NOT PAYING ATTENTION | ● ALWAYS FACE THE WORK AND NEVER LET THE JOINT OF CASING OUT OF YOUR SIGHT WHLE JOINTS ARE TAILED IN ● MAKE SURE YOU STAND TO THE SIDE OF THE CASING AND ALWAYS HAVE AN ESCAPE ROUTE ● NEVER STAND BETWEEN EQUIPMENT AND THE DERRICK LEG OR OTHER EQUIPMENT SO YOU ARE NOT CAUGHT BETWEEN THE TWO AND INJURED ● DO NOT DISTRACT WORKING PERSONNEL ON THE RIG FLOOR |
| ● V-DOOR OPERATORS | ● NOT HAVING A PERSON OR HAVING MORE THAN ONE PERSON FLAGGING IN THE OPERATORS COULD INJURE OTHERS BY CREATING CONFUSION | ● ONLY ONE PERSON SHOULD BE DESIGNATED AS THE FLAGGER FOR THE OPERATION AND SHOULD WEAR THE DESIGNATED VEST IF REQUIRED ● USE HAND SIGNALS TO COMMUNICATE WITH OPERATORS TO CLEARLY UNDERSTAND INSTRUCTIONS |
| Safety First - Safety Always Plan and Execute for Success | Page: 2 of 8 |